Winder Hydraulic Installation

Client: Whakatane Board Mill
Project Head: Gysbertus De Lange
Category: Hydraulics
Date: July 2023

 

McRaes Global was selected to carry out the installation of the Winder hydraulic system for Whakatane Board Mill as part of their site-wide upgrades. The main challenges of this project were centered around the equipment to be installed was all second-hand in varying states of disassembly, a very tight time frame in which to complete all installation work during the shut and managing the dynamics of working on such a large project with so many variables.

A considerable amount of time was invested pre-shut assessing how individual components and sub-assemblies tied together to build a complete hydraulic system. This information was then overlayed with 3D models and photos of the plant and equipment to allow us to plan pipe routes and compile material requirements.

The scope of this project rapidly grew to include installation of the filed piping for the lubrication, pneumatic and grease systems also. To meet this demand we were able to call on additional personnel and equipment resources from our Auckland and Whangarei branches.

A successful installation of all systems was carried out under very challenging conditions.

Figure 1: Pipe route planning, pre shut machine setup.
Figure 2: Pipe route planning.
Figure 3: Section of complete tube install on site.

IMG MCRAES GLOBAL PROJECTS

$

BALE FORMING PRESS

$

KOMATSU

$

KILN CRUSHER

$

MEGA YACHT YAS

$

HYDRAULIC SYSTEM UPGRADE

$

DRILL RIG MAST HYDRAULIC CYLINDER

$

WINDER HYDRAULIC INSTALLATION

$

SLASHER DECK HYDRAULICS

You might Be interested in..


BALE FORMING PRESS

KOMATSU

KILN CRUSHER

MEGA YACHT YAS

HYDRAULIC SYSTEM UPGRADE

DRILL RIG MAST HYDRAULIC CYLINDER

WINDER HYDRAULIC INSTALLATION

SLASHER DECK HYDRAULICS